Arrival port checklist
Upon 1 hr. notice:
- Stop FWG and shut valves.
- Change over to high sea suction.
- Soot blow Auxiliary boiler, check firing amd put on auto mode.
- Check all air compressors oil level and put on auto mode.
- Charge both air bottles and drain any water from bottles and air dryer.
- Shut and lock bilge overboard valve and hand over key to cheif engineer. Ensure that all bilge suction valves are shut, however not locked. [Thr security seals may be used to avoid inadvertent opening of any bilge suction valve]
- Start additional generator for power to mooring machinery, thrusters, deck water, etc.,
- Shut steam to D.B F.O.T's.
- Put on sewage plant and changeover valves.
At standby
- start additional generator as required.
- At standby record M/E counter, flowmeter readings, L.O sump and cyl. oil tank levels.
- Ensure adequate manpower available for arrival port.
At FWE (finish with engine)
- Take over control from bridge to ECR and stop auxiliary blower.
- Open indiactor cocks and engage turning gear.
- Turn M/E by turning gear with cylinder lubricator rotated 20-30 turns each for about 15 mins.
- Cover M/E T/C suction filters.
- Put M/E on preheat and maintain temperature.
- Stop unnecessary machinery and put off breakers.
- shift generator load and stop as required.